Look below at our crazy adventure to transform a warehouse into the Ultimate Sports Center. We are documenting the growth process using weekly photos of key areas: Before, During and After. This also show the areas we have for rent and how they can be used. Enjoy, we do!
BEFORE circa December 30, 2009
-warehouse going to be transformed into 14 court sport facility
Before THE WALL was built!
January 21- THE WALL is finished. 11 days after the The WALL was started its massive imposing, banner begging self is complete. The wall measures over 28' high and 564' of total length. The DSs and setter's dream.

Before Mezzanine outlook built, wall and doors painted and signs
Mezzanine with viewing area from 200 person banquet room, directional signs, and vending machines.
Sunday, January 16th- 4 courts down middle lane and practices/academies have already begun
January 22, 2010- I Beam pads, netting between courts, and entry rugs for claeaning shoes
February 5th, 2010- 1st Torunament, 2 days, 56 Adult Teams, Air City Tournament
-Improvements in last two weeks: 7 courts, side pads, vinyl wall in back installed, snack vending machines, directional signs, snack bar open, downstairs bathrooms operational, viewing window blown out, tile installed banquet room, hallways,
BEFORE- Banquet room/Snack bar circa December 30, 2009


AFTER- February 5, 2010 - transformation of banquet room nearing completion. Viewing window cut out, tile installed, snack bar open, tables and chairs for patrons. Banquet room will seat 200 people!
Feb. 5, 2010- snack bar open
Feb. 5, 2010- close up of Mezzanine Viewing window w/ 2 cool dudes and our 1st Tournament going on in the background!
Pre Fitness Center Remodel- January 2010
PARKING AT ULTIMATE SPORTS CENTER, NO PROBLEMO! STILL HAD PLENTY OF SPACE TO PARK, AND ABOUT 25% OF PARKING LOT WAS NOT CLEARED OF SNOW.